Greenfield Energy Co-Generation Facility

The facility is a natural gas-fired power plant consisting of three gas turbines and a single steam turbine operating in combined cycles. Maaten Construction Limited constructed five pre-engineered buildings on a design-build basis, as well as four conventional buildings for the project.

Conventional Construction:
• Steam Turbine Generator (STG) Building
• Boiler Feed Pump (BFP) Buildings 1,2 and 3

Design-Build of Pre-Engineered Buildings and Foundations:
• Administration Building
• Cycle Chemical Feed Building
• Water Treatment Building
• Warehouse Building
• Cooling Tower Chemical Feed Building